Background

As Leonard Cheshire were relocating there office from unit 6a to unit 8, we carried out some alterations to unit 8 before they relocated, this involved

Forming a stud partition wall from one end of the room to the other which would then create two additional offices for storage and office staff.

We fitted some additional fire/smoke alarms, along with a complete intruder alarm system.
In unit 6a we had to bring the inside back to where it was originally before they moved, this involved disconnecting the power supply and making safe of all electrics.

Once this was complete we could then take down the existing partition wall that they had erected when they first moved in, all walls and timber work received a fresh coat of paint.

All the existing carpet was lifted and replace with new, we then performed a pedeoric survey off all electrics

Project Address

Unit 6a/8  Stephenson Court
Priory Business Park
Fraser Road
Bedford
MK44 3WJ

Contract Details

Start Date June 2009
Completion Date July 2009
No. of Accidents 0